Delay Cost Calculator | Gallatin Valley Site Services
Cost of Delay

What does a late site package actually cost you?

Landscape and site work sit between substantial completion and a building you can hand over. Move three sliders and see the number.

Total construction value $14.0M
Target substantial completion
In the Gallatin Valley this is the input that decides everything.
Weeks the site package runs late 4 weeks
Critical path days only. Slip that eats float costs nothing.
Total delay exposure
$0
Days to final CO
0
Cost per week late
$0
Site package value
$0

Your project against the Bozeman install window

Can install Ground closed
Planned
Actual

Start a plan review
Gallatin Valley Site Services

Delay exposure report

01.

Hard delay

Hard delay subtotal$0
02.

Carrying an open job

Carry subtotal$0
Total delay exposure
$0
Bid tab break even

Buy the schedule back

$0

They walk off

$0

03.

Assumptions

Nothing here is hidden. These are the defaults the model runs on, drawn from published industry benchmarks and current Gallatin Valley market data. Change any of them and every number above updates. If a figure looks wrong for your project, it probably is. Change it.

Sources and method. Liquidated damages use the widely cited reasonableness band of $20 to $25 per day per $100,000 of contract value. Extended field overhead uses the standard daily rate method, total general conditions divided by contract duration, discounted by a tail factor because closeout general conditions run below the project average. Unabsorbed home office overhead follows a simplified Eichleay allocation and is recoverable only on compensable delay. Subcontractor default replacement uses the Surety and Fidelity Association of America range of 1.5 to 3 times subcontract value, defaulted to the low end. Completion bond sizing at 150 percent of remaining work reflects common practice among building departments issuing a temporary certificate of occupancy over incomplete site work. Construction loan pricing reflects a 2026 weighted average near 8.4 percent, SOFR plus a 250 to 400 basis point spread. Lease rates reflect Bozeman commercial averages near $24 per square foot. Season dates follow NOAA thirty year normals for the Gallatin Valley: last spring frost around May 20, first fall frost around September 15, roughly 118 frost free days. This estimates exposure. It is not a claim, a legal opinion, or a substitute for your scheduler.